Everest WRF
Progress
Report
Phase 1 – Demolition & Outfall
Budget - $2.3M
Completion date – June 2006
Capacity Available – July 2006
Phase 2 – Minor Modifications
Progress – Under Construction
Budget - $8M
Completion Oct 2007
Phase 3 - Upgrade
Expansion : 8.5 to 13.4 MGD
Progress – Under Construction
Budget – $62M
Completion date – Feb 2009
Capacity (Partial) Available – June 2008
Budget - $2.3M
Completion date – June 2006
Capacity Available – July 2006