Everest WRF

Progress Report

Phase 1 – Demolition & Outfall
   Budget - $2.3M
   Completion date – June 2006
   Capacity Available – July 2006
Phase 2 – Minor Modifications
   Progress – Under Construction
   Budget - $8M
   Completion Oct 2007
Phase 3 - Upgrade
   Expansion : 8.5 to 13.4 MGD
   Progress – Under Construction
   Budget – $62M
   Completion date – Feb 2009
   Capacity (Partial) Available – June 2008