SW RO Water Plant & Wells
Progress
Report
Phase 1 – Production Wells (#8)
Cost - $2.9M
Completion date – April 2006
Progress – Complete
Phase 2 – Transmission Pipeline
Cost - $3.1M
Completion date - Nov 2006
Progress – Complete
Phase 3 – Expansion from 15 to 18.1 MGD
Progress – Under Construction
Budget – $7M
Completion date – Late 2007
Capacity Available – Mid 2007