SW RO Water Plant & Wells

Progress Report

Phase 1 – Production Wells (#8)
  Cost - $2.9M
  Completion date – April 2006
  Progress – Complete
Phase 2 – Transmission Pipeline
  Cost - $3.1M
  Completion date - Nov 2006
  Progress – Complete
Phase 3 – Expansion from 15 to 18.1 MGD
  Progress – Under Construction
  Budget – $7M
  Completion date – Late 2007
  Capacity Available – Mid 2007