Cape Coral Utilites Exspansion Web Site
  Last Updated: 8/5/2008 www.capecoralutilityexpansion.com 
Home Maps Process Links Contact Us FAQ
Process http://www.capecoral.net
CONSTRUCTION  -  HOOK-UP  -  PAYMENT PROGRAM

Construction
What is the process for construction?
In general, there are four basic stages to the construction process.
  • Planning and Design
  • Pre-Construction
  • Construction
  • Post Construction
Planning and design primarily involve "behind the scenes" preparation by the City and the engineers to assure the most cost-effective, easy-to-operate and easy-to-maintain solution for the residents of Cape Coral. If you live or work in the affected areas you may see surveyors taking measurements of existing conditions for the engineers to use in developing designs.
The pre-construction phase is when the pace steps up a notch but still may not be evident to the general public.  Activities include:
  • Competitive bidding by a pre-qualified group of local contractors. KBR reviewed the qualifications of area contractors and developed a "short list" of the most qualified.
  • Documenting existing conditions - crews will videotape properties, streets, and driveways so they can put things back when construction is complete.
  • Establishing right-of-ways - specifying where on each lot construction will take place.
  • Setting staging areas - locating sites where equipment and materials can be kept while the utilities are under construction.
  • Preparing the documentation necessary to obtain the required permits.
Some of the things the video crews will be paying close attention to when documenting conditions include:
  • Driveways
  • Landscaping
  • Grass
  • Mailboxes
  • Conditions of houses and buildings
  • Seawalls
  • Fences

We want to make sure that each of these items are restored to as equal or better condition after construction is complete.

Our goal is to keep disruption to a minimum. Only a short section of trench will be open at a time and even that will be back-filled or plated over at night. During construction, temporary locations will be provided for school bus pick-up, trash pick-up and mail delivery as required.
  • Access to homes & businesses
  • Special needs & Emergency vehicles
  • Mail delivery
  • School bus stops
  • Garbage pickup

This brings us to the next phase in the process and the most visible—construction. During this phase, utility lines will be installed in the ground. But before that, notifications will be provided to property owners with information about construction dates using door hangers and printed notices.

The first step in the construction process is to remove the existing road surface.

Next, the existing water table must be lowered to facilitate digging in the immediate area. A series of shallow well points will be installed and the water pumped to a nearby canal.

Barriers will be constructed to minimize the sound produced by the pumps, which will oftentimes be running around the clock.

Gravity sewer lines and manholes are installed under the streets. They range in depth from 4 feet to almost 20 feet down. Since these lines are deeper, progress is slower and disruption is greater for sewer than for water and secondary water.

Safety standards require sloping these trenches. Trench boxes will be used for the deeper excavations, but in many cases the entire width of the road will be dug up.

The water and secondary water lines are then installed. These lines are much shallower and are installed in much narrower trenches along either side of the road.

In some cases, the driveways will need to be cut in order to install these shallow lines. A narrow trench will be made and a temporary gravel repair will be provided at the end of the workday.

The final driveway repair will consist of removal and replacement of a minimum of 3 feet of driveway apron. Additional reinforcing steel will also be installed to beef up the corners. 

This is a picture of final restoration completed on the North Loop project.

For undeveloped lots, seeding and mulching are provided instead of sod.
>>Continue on to learn more about the right-of-way.
Home  -  Maps  -  Process  -  Links  -  Contact Us  -  FAQ
Copyright 2008,  MWH   All rights reserved.